Stagecoach Depot
Eddington Lane, Kent

Details

Our team helped ALS complete Stagecoach’s new bus station in Herne Bay. Prior to the project, large vehicles were unable to access the large site. Our role was to solve this problem by constructing a new road and footpath.

The job entailed a full re-surfacing and white lines package, gully works, temporary resurfacing, plus surface and wastewater drainage. Traffic management was also required to keep disruption limited.

Despite a tight deadline, the job was completed on schedule in the weeks before Christmas. The new facility is now operational and meets all of Stagecoach’s needs.

Project Facts

  • Duration 6 weeks
  • Value £200k
  • Client ALS Civil Engineers Ltd