Thorn Sluice
Faversham, Kent

Details

We installed 3500m2 of TTE module to create a permanent access road to the sluice. The project required concrete works, soft and hard landscaping, plus the abandonment of two existing pipes. The job also needed detailed planning to accommodate the rising and falling tides.

The TTE model we used was the first in the country; therefore the supplier and the environmental agency, as well as the client, were eager to see how the track performed. The results were excellent.

We took part in a successful review day that was attended by many representatives. Because the work was carried out in a SSSI, we kept environmental disruption to an absolute minimum.

This project shows our ability to work flexibly, embrace new technologies and care for the environment.

Project Facts

  • Duration 10 weeks
  • Value £100k
  • Client JT Mackley